Mean time between failures

Mean time between failures is the average operating time between one failure of a repairable machine and the next, calculated as running hours divided by the number of failures.

What it means

A longer figure means a more reliable machine. To calculate it, add the hours the machine was actually running over a period and divide by the number of breakdowns. It is useful for comparing machines, judging whether maintenance is working and scheduling parts replacement before the usual failure point.

Example

A cutting machine ran 1,200 hours in six months and failed 4 times. Its mean time between failures is 300 hours, so the team plans a bearing check at around 250 hours of running.

Records and checks

  • Record operating hours per machine and each failure date, with its cause.
  • Verify run hours against meter readings or shift logs, and decide what counts as a failure before you begin.
  • The maintenance lead calculates it; production reviews machines with falling figures.

Common mistakes

  • Using calendar hours instead of running hours.
  • Counting minor adjustments as failures in one period and ignoring them in the next.