Process lead time
Process lead time is the total elapsed time from the moment work enters a process until the finished output leaves it, including all waiting, queuing and moving.
What it means
It is the customer's view of how long things take. Most of it is usually waiting, not working, so a job with 2 hours of work may have a lead time of 5 days. Lead time reduction therefore comes mainly from cutting queues, handover delays and batch waiting, not from making people work faster.
Example
A job card for a sheet metal part shows 3 hours of cutting, bending and welding, but the part takes 6 days from order release to packed, because it waits for material, then queues at the press brake and again for painting.
Records and checks
- Record the start date and time, the end date and time and the main waiting points of each job.
- Verify with job cards or stage scans, so waiting times are captured and not guessed.
- The planner calculates the average, and the production head targets the longest waits first.
Common mistakes
- Quoting working time as lead time, so delivery promises are far too short.
- Looking for savings inside the operations when most of the time sits between them.