Production lead time

Production lead time is the total elapsed time from releasing a production order to completing the goods, including setup, running, waiting, moving and inspection.

What it means

It is usually far longer than the actual processing time. A job needing 6 hours of machining may spend days waiting in queues, in transit between departments and in inspection. Lead time is what planners use to decide when to release orders and what customers experience as delivery time. Cutting waiting time is normally the easiest way to shorten it.

Example

A Moradabad metalware workshop times a batch of brass bowls. Cutting, spinning, polishing and plating together involve about 9 hours of work, but the batch takes 11 days from release to packing, mostly waiting for plating slots. Booking plating capacity two days ahead cuts the lead time to 7 days.

Records and checks

  • Record the release date, each operation's start and finish, and the completion date.
  • Verify the lead time from actual completed jobs, using recent data, not a single best case.
  • The planner calculates it; the production head reviews where the waiting time is greatest.

Common mistakes

  • Quoting delivery from processing hours alone, ignoring waiting and transport time.
  • Setting one lead time for all batch sizes, when large batches take much longer.