Rework
Rework is the extra work done on a defective item to bring it within specification, so it can be sold as good instead of being scrapped.
What it means
Some defects can be fixed. A shaft can be re-ground, a weld repaired, a label stuck again or a garment re-stitched. Rework saves material already spent, but costs labour, machine time and delay. A piece should be reworked only if the repair is reliable and the cost is lower than scrapping and making a new one.
Example
Forty switch panels have a wrongly drilled hole. Re-drilling and plugging takes 15 minutes each at ₹6 a minute labour, so ₹90 per panel. Making a new panel costs ₹700, so rework is worth it, provided the plug is inspected.
Records and checks
- Record the quantity, defect, rework method, time spent, cost and who did the work.
- Verify through re-inspection that every reworked piece now meets the specification before it re-enters stock.
- The quality inspector re-inspects, and the supervisor tracks rework hours.
Common mistakes
- Not costing rework, so a product that looks profitable is quietly losing money.
- Skipping re-inspection after repair, so a bad fix reaches the customer.