Water balance

A water balance is a statement matching all water entering a site against all water leaving, used, stored or lost, so unexplained losses become visible.

What it means

Inputs include municipal supply, borewell, tanker and recycled water. Outputs include water in the product, process use, cooling and boiler losses, wastewater, evaporation and leaks. Inputs should equal outputs plus any change in storage. A large gap suggests leaks, unmetered use or reading errors. Industries use it in audits and for planning recycling, and some need it for environmental approvals.

Example

A dairy in Anand takes in 120 kilolitres a day. Its records show 70 in process and cleaning, 25 in cooling, 15 in wastewater, and 4 in evaporation, leaving 6 kilolitres unexplained. A pipe leak under the yard is later found.

Records and checks

  • Record inflows by source and outflows by use, each from a meter or a calculated estimate.
  • Verify that the figures close within a small tolerance and flag an unexplained difference.
  • The utilities in charge prepares it monthly and the plant head reviews gaps.

Common mistakes

  • Estimating use instead of metering, then trusting a balance that hides a leak.
  • Ignoring changes in tank level between the start and end of the period.