How to recover when the production or service plan slips

Every plan slips sooner or later: a machine stops, two people are absent, a rush order lands. This guide shows how to see the slippage early, reset the plan with real numbers and agree the next day's work at a short daily huddle instead of letting delays pile up silently.

The example is an auto-component job shop in Rajkot with six machines and two shifts, but the same routine suits a repair workshop or a clinic with fixed appointment slots.

Why this matters

A late order rarely comes from one big failure. It comes from a few lost hours each day that nobody wrote down, so by the time the customer calls, the delay is days. A plan that is compared with actual output every day shows you the gap while it is still small enough to close with overtime, a swap of jobs or a call to the customer. It also gives you honest dates to quote.

Before you start

  • A demand list: confirmed orders with quantities and promised dates, plus any expected repeat orders.
  • A capacity board: each machine, bench or person, the hours available per shift and any planned stoppage.
  • Standard time per job, even if it is only a rough average from past work.
  • A daily plan sheet and a daily output sheet.
  • A fixed time for the huddle and the names of who attends.

Step by step

  1. Estimate the demand. The planner lists what must be delivered in the next two to four weeks, using confirmed orders and recent patterns. For the Rajkot shop, that is the open orders for brackets and housings, with a small buffer for the regular customer who often adds quantity at short notice.
  2. Compare required and free capacity. The shift supervisor works out how many machine hours each job needs and sets that against the hours each machine can actually give, after maintenance and changeovers. Where required hours exceed free hours, the gap is written next to that week on the capacity board.
  3. Build the dated schedule and resolve clashes. The operations manager decides which job runs on which machine on which day, and what to do about clashes: outsource part of the work, move a lower-priority job, add a shift or tell a customer that a date will move. Each decision is written on the daily plan, not left in conversation.
  4. Capture progress through the day. The planner records how many pieces each machine actually produced, how many people were present and what stopped work, with times. A short note such as "Machine 3 down 90 minutes, tool change" is enough, as long as every shift gets an entry.
  5. Hold a ten-minute huddle. At the end of the shift, the shift supervisor and the planner review planned against actual output with the operations manager. They agree what moves to tomorrow, whether overtime or a swap is needed and which customers must be told about changed dates.
  6. Reset the plan from facts. The planner updates the schedule with real output rather than the old plan, and records the huddle's decisions with a name and date next to each. The next morning begins from that revised plan.

Who does what

RoleWhat they doRecord they own
PlannerEstimates demand, records daily output and slippage, resets the scheduleDemand forecast and daily output record
Shift supervisorChecks capacity, reports stoppages, brings floor facts to the huddleCapacity board and huddle notes
Operations managerResolves clashes, decides on overtime, outsourcing or date changesDaily plan and huddle decisions

Common mistakes

  • Planning on full machine hours, ignoring maintenance, changeovers and absentees.
  • Recording output only at week end, when nobody can recall why a day went badly.
  • Keeping the plan with the planner alone, so supervisors learn of changes from the floor.
  • Promising customer dates before checking free capacity.
  • Using the huddle to find fault instead of making three clear decisions for tomorrow.

How to tell it is working

  • Capacity gap. For each week, subtract free hours from required hours. A positive number is a shortfall; watch that you decide what to do about it before the week starts, not after.
  • Missed slot. Count planned jobs that did not start or finish in their planned slot, divided by all planned jobs for the week. It should be shrinking, and every miss should have a one-line reason.
  • Unrecorded output. Compare shifts worked with shifts that have an output entry, and count the shifts with no entry. Aim for none, since every missing entry is a day the plan cannot be trusted.

Questions people ask

Who owns plan to deliver?

The operations manager owns the plan and the promised dates, while the planner owns the daily records and the supervisor owns the floor facts. When a date slips, the manager decides who tells the customer.

What is the minimum record for plan to deliver?

Keep the demand list, the capacity per machine, the daily plan, the actual output with stoppage reasons and the huddle decisions. These five let you compare plan against reality every single day.

When should a case stop?

A job stops being tracked when it has been delivered and the output matches the order. If the order is cancelled or put on hold, record who decided and when, then take its hours out of the capacity board.

Can a spreadsheet support this stream?

Yes, a weekly sheet with machines in rows and days in columns, plus a second sheet for daily output, is how many small shops do it. Keep one master copy and update it only at the huddle so there are never two versions.

What should the owner review?

Once a week, look at the capacity gap for the coming fortnight, the number of missed slots and the shifts with no output record. Ask which customers have been told about a new date.